Singapore Downtown Line Stage 2 Contract 915 / Shield Tunnel
Summary
We initiated the project with installing Slurry treatment equipment from December 2010, and completed 4.3km length of tunneling with 3 different TBM Machines. We expected many difficulties such as operating 3 TBM machines, tunneling bed rock and complex foundation but successfully completed 4 penetrations by overcoming trials such as subsidence while tunneling complex foundation, abrasion of numerous cutter and pipe, and transformed cutter-head because of the hard rock tunneling.
-
Begin 2010.01
Client LTA
-
Location Singapore
Explanation Slurry : Length - 4,634(M), Diameter - 6,650(mm)
Ground : Bukit timah Granite, Complex Stratum