Singapore CRL CR108 / Dwall & Bored Pile

Summary

The construction of the Pasir Ris transfer station for the opening of the Cross Island Line MRT connecting eastern and western Singapore, and Daewoo Engineering & Construction and Dong-A Geology participated as Joint Venture. It is an extension of the existing EWL station, with an underground continuous wall depth of up to 86m and a low head cutter room under the MRT currently in operation.

  • Begin 2021.09

    Client LTA(Land Transport Authority)

  • Location Singapore

    Explanation 1. Dwall : T1000~1500, 290,135㎥ (Lowhead 14,068㎥)
    2. Cwall : T800, 279,500㎥ (Lowhead 4.634㎥)

Youtube
CS CENTER