UAE Abu Dhabi STEP Deep Tunnel Sewer Contract T-01 / Shield Tunnel

Summary

It was the first project in Abu Dhabi to apply Shield TBM. The tunnel is 16km length and 3 EPB type of shield TBM Machines with 5.3m in diameter were assigned. Each TBM Machine excavated about 5km length and we excavated 750m in a month which was the best record among the Korean construction companies at that time.

  • Begin 2012.03

    Client ADSSC

  • Location Abu Dhabi

    Explanation EPB : Length - 16,032(M),
    Diameter - 5,320(mm), 3span, Complex Stratum