Korea Incheon International Airport Railroad Phase 2/Shield Tunnel

Summary

To provide better transportation service to the customer of T2, this project is to connect the railroad to T2 by pass through the underground of Third Runway. The project was carried out with Shield Tunnel method for the smooth operation of runway, connectivity with 3rd project and easy maintain.

  • Begin 2014.08

    Client Korea Rail Network Authority

  • Location Incheon, Republic of Korea

    Explanation Slurry, LENGTH-2,277(M), DIAMETER-7,930(mm), GROUND : weathering soil,reclamation so