Korea Bujeon~Masan Build-Transfer-Lease Construction work / Bored Pile work(3,4 Zone)

Summary

This project is aim to provide convenience to local residents and develop tourism resources, and also the route between Yeongnam districts and Honam districts has been made shortened for accelerating interchange. Our company has performed 212piles of RCD method works and 189,376m of DCM works in 3rd stage, and 132piles of RCD method works in 4th stage. The DCM works in 3rd stage is the largest scale of land DCM works in Korea and height restriction areas. From the remodeling equipments to the constructing method, our technologies have been integrated into the construction method, which will be an opportunity for our technologies to positive growth.

  • Begin 2015.03

    Client Smartrail Co., Ltd.

  • Location Busan, Republic of Korea

    Explanation DCM Length : 80,809m, 189,376m (D=1,200mm, 2 drivers)