Korea Ulsan New Port Northen Revetment Breakwater construction

Summary

It is a construction of Revetment breakwater to block the waves (swelling wind wave) flowing from the south of Ulsan New Port to the North Port District. To ensure the smooth operation of five berths in the North Port area, including Northeast Asia Oil Hub (Phase 1), wood, cement, and liquid chemical docks, the construction of a 605-meter Bangpa Lake and the static temperature of the North Port of Ulsan New Port were constructed using the DCM method. In addition, it helped the smooth operation of Ulsan New Port North Port by blocking the Goparang by improving the high-level weak seabed layer of Goga Subi so that stable caisson structures could be installed.

  • Begin 2016.05

    Client Ulsan Regional Office of Oceans and Fisheries

  • Location Ulsan, Republic of Korea

    Explanation DCM : L = 86,536m
    (D=1,350mm, 4 drivers)

Youtube
CS CENTER