Major Performance
-
![](/upload/board_business_eng/Singapore Thomson Line T213 t.jpg)
Singapore Thomson Line T213
-
Period
2014.04 ~ 2015.07
-
Client
LTA
-
Location
Singapore
-
Explanation
D-Wall Method
-
![](/upload/board_business_eng/해운대 LCT 공사1.jpg)
Korea Haeundae LCT Construction
-
Period
2013.11 ~ 2015.04
-
Client
LCT
-
Location
Busan, Republic of Korea
-
Explanation
Earthworks, underground continuous walls, on-site percussion piles, PRD, RJP, E/A, facilities, measurement management
-
![](/upload/board_business_eng/Singapore Cable Tunnel NS2 Dwall 공사 1.jpg)
Singapore Cable Tunnel NS2 Dwall
-
Period
2013.11 ~ 2018.05
-
Client
SP Power Grid
-
Location
Sembawang shaft, Singapore
-
Explanation
Diapharagm Wall Method, Excavating:D=6,990mm
-
![](/upload/board_business_eng/천마산 터널 건설공사 t.jpg)
Korea Mt. Cheonma Tunnel Construction/Tunnel Work
-
Period
2013.10 ~ 2019.01
-
Client
Mt. Cheonma Tunnel Corporation
-
Location
Busan, Republic of Korea
-
Explanation
NATM, 2 Lane 2Way tunnel Length 1.5km (Two-lane Tunnel in both direction)
-
![](/upload/board_business_eng/인천국제공항 T2전면시설 t.jpg)
Korea T2 Section Soil Excavation & Piling Constrution(Including Underground Structure of Station
-
Period
2013.10 ~ 2015.12
-
Client
Incheon International Airport Corporation
-
Location
Incheon, Republic of Korea
-
Explanation
Diameter Φ2500 138 pieces,
Diameter Φ2000 63 pieces
-
![](/upload/board_business_eng/DTL STAGE2 C918A.jpg)
Singapore DTL STAGE2 C918A/Bored-Tunnel
-
Period
2013.09 ~ 2015.04
-
Client
LTA
-
Location
Singapore
-
Explanation
Shield Tunnel 2
( S604 : 814m, S605 : 863m )